MORAJ OPULENCE
P51900032370
Under construction
Currently within its planned build window. Watch the deadline and any new extensions.
Where this project stands
The journey from RERA registration to completion, in order.
Approaching the deadline.
Registered with RERA
29 Dec 2021Original promised completion
28 Dec 2026The deadline the builder committed to at registration.
Today — in progress
About 6 months left until the deadline.
Timeline & delay
Key dates and how they compare to what was promised.
29 Dec 2021
When the project was registered with RERA.
28 Dec 2026
The deadline committed to at registration.
28 Dec 2026
After all approved extensions.
—
Handover date, when available.
On track0 mo
How far past deadline an ongoing project is.
1
More extensions can signal execution risk.
Complaints
Buyer complaints recorded on the official registry.
Complaints on this project
1
Complaints against the builder
0
Often reported per project on MahaRERA
Extension history
Each time the completion deadline was officially pushed back.
| From | Extended to | Reason |
|---|---|---|
| 28 Dec 2026 | 31 Dec 2029 | MahaRERA extension (original vs revised completion date) |
About the builder
How this developer has performed across all their tracked projects.
Strong track record
Tracking 1 project — 0 delivered, 1 still active. Limited history — read the project list before drawing conclusions.
Official records
Builder: MORAJ AHN DEVELOPERS LLP (NAME:MORAJ AHN DEVELOPERS LLP)
Data last refreshed 21 Jun 2026.