Island Cove

P51900046369

Mumbai City, MaharashtraOthersIn progress

Under construction

Currently within its planned build window. Watch the deadline and any new extensions.

Where this project stands

The journey from RERA registration to completion, in order.

Registered 22 Jun 2022Due 31 Aug 2028

Within the planned build window.

  1. Registered with RERA

    22 Jun 2022
  2. Original promised completion

    31 Aug 2028

    The deadline the builder committed to at registration.

  3. Today — in progress

    About 26 months left until the deadline.

Timeline & delay

Key dates and how they compare to what was promised.

22 Jun 2022

When the project was registered with RERA.

31 Aug 2028

The deadline committed to at registration.

31 Aug 2028

After all approved extensions.

Handover date, when available.

On track0 mo

How far past deadline an ongoing project is.

1

More extensions can signal execution risk.

On MahaRERA this project's registration status is New and its completion status is Active. “Registration status” is the legal state of the filing; “completion status” is how far along construction is.

Complaints

Buyer complaints recorded on the official registry.

Complaints on this project

2

Complaints against the builder

0

Often reported per project on MahaRERA

Extension history

Each time the completion deadline was officially pushed back.

FromExtended toReason
31 Aug 202831 Dec 2028MahaRERA extension (original vs revised completion date)

About the builder

How this developer has performed across all their tracked projects.

Strong track record

Tracking 1 project — 0 delivered, 1 still active. Limited history — read the project list before drawing conclusions.

1 projects0 delayed (0%)

See LH Residential Housing Private Limited's full track record →

Official records

View this project on the MahaRERA portal

Builder: LH Residential Housing Private Limited (NAME:LH Residential Housing Private Limited)

Data last refreshed 21 Jun 2026.