VIVA
P51900047459
Behind schedule
This project is about 6 months past its latest deadline and is not yet marked completed.
Where this project stands
The journey from RERA registration to completion, in order.
Past deadline by ~6 months.
Registered with RERA
2 Nov 2022Original promised completion
31 Dec 2025The deadline the builder committed to at registration.
Today — still not completed
About 6 months past the latest deadline.
Timeline & delay
Key dates and how they compare to what was promised.
2 Nov 2022
When the project was registered with RERA.
31 Dec 2025
The deadline committed to at registration.
31 Dec 2025
After all approved extensions.
—
Handover date, when available.
6 mo overdue5.7 mo
How far past deadline an ongoing project is.
1
More extensions can signal execution risk.
Complaints
Buyer complaints recorded on the official registry.
Complaints on this project
0
Complaints against the builder
0
Often reported per project on MahaRERA
No complaints found in the data we have. This isn't a guarantee — verify on the portal.
Extension history
Each time the completion deadline was officially pushed back.
| From | Extended to | Reason |
|---|---|---|
| 31 Dec 2025 | 30 Jun 2027 | MahaRERA extension (original vs revised completion date) |
About the builder
How this developer has performed across all their tracked projects.
Poor track record
Tracking 1 project — 0 delivered, 1 still active. 1 of 1 (100%) ran late. Limited history — read the project list before drawing conclusions.
Official records
Builder: LIVSTONE BUILDERS LLP (NAME:LIVSTONE BUILDERS LLP)
Data last refreshed 21 Jun 2026.