Central Park

P51900053390

Mumbai City, MaharashtraResidential / Group HousingIn progress

Under construction

Currently within its planned build window. Watch the deadline and any new extensions.

Where this project stands

The journey from RERA registration to completion, in order.

Registered 27 Oct 2023Due 30 Jul 2028

Within the planned build window.

  1. Registered with RERA

    27 Oct 2023
  2. Original promised completion

    30 Jul 2028

    The deadline the builder committed to at registration.

  3. Today — in progress

    About 25 months left until the deadline.

Timeline & delay

Key dates and how they compare to what was promised.

27 Oct 2023

When the project was registered with RERA.

30 Jul 2028

The deadline committed to at registration.

30 Jul 2028

After all approved extensions.

Handover date, when available.

On track0 mo

How far past deadline an ongoing project is.

0

More extensions can signal execution risk.

On MahaRERA this project's registration status is New and its completion status is Active. “Registration status” is the legal state of the filing; “completion status” is how far along construction is.

Complaints

Buyer complaints recorded on the official registry.

Complaints on this project

1

Complaints against the builder

0

Often reported per project on MahaRERA

About the builder

How this developer has performed across all their tracked projects.

Strong track record

Tracking 2 projects — 1 delivered, 1 still active. No delays recorded so far. Limited history — read the project list before drawing conclusions.

2 projects0 delayed (0%)100% on time

See H. M. Holdings's full track record →

Official records

View this project on the MahaRERA portal

Builder: H. M. Holdings (NAME:H. M. Holdings)

Data last refreshed 21 Jun 2026.