Prajapati Magnum Phase II
P52000001425
Delivered on time
Marked completed on the registry on or before the promised deadline.
Where this project stands
The journey from RERA registration to completion, in order.
Completed.
Registered with RERA
28 Jul 2017Original promised completion
30 Jun 2023The deadline the builder committed to at registration.
Marked completed on the portal
Shown as completed on the official registry (no exact date scraped).
Timeline & delay
Key dates and how they compare to what was promised.
28 Jul 2017
When the project was registered with RERA.
30 Jun 2023
The deadline committed to at registration.
30 Jun 2023
After all approved extensions.
—
Handover date, when available.
On track0 mo
How far past deadline an ongoing project is.
1
More extensions can signal execution risk.
Complaints
Buyer complaints recorded on the official registry.
Complaints on this project
0
Complaints against the builder
0
Often reported per project on MahaRERA
No complaints found in the data we have. This isn't a guarantee — verify on the portal.
Extension history
Each time the completion deadline was officially pushed back.
| From | Extended to | Reason |
|---|---|---|
| 30 Jun 2023 | 28 Dec 2025 | MahaRERA extension (original vs revised completion date) |
About the builder
How this developer has performed across all their tracked projects.
Strong track record
Tracking 2 projects — 2 delivered, 0 still active. No delays recorded so far. Limited history — read the project list before drawing conclusions.
Official records
Builder: PRAJAPATI DEVELOPERS (NAME:PRAJAPATI DEVELOPERS)
Data last refreshed 21 Jun 2026.