BANDAL VED BHUMI-PHASE 2
P52000003424
Delivered — but late
This project was completed about 32 months after its original promised deadline.
Where this project stands
The journey from RERA registration to completion, in order.
Completed.
Registered with RERA
5 Aug 2017Original promised completion
28 Aug 2022The deadline the builder committed to at registration.
Revised deadline after extensions
28 Apr 2025Pushed back ~32 months across 1 extension.
Marked completed on the portal
Shown as completed on the official registry (no exact date scraped).
Timeline & delay
Key dates and how they compare to what was promised.
5 Aug 2017
When the project was registered with RERA.
28 Aug 2022
The deadline committed to at registration.
28 Apr 2025
After all approved extensions.
—
Handover date, when available.
32 mo delay32 mo
How late the finished project was.
1
More extensions can signal execution risk.
Complaints
Buyer complaints recorded on the official registry.
Complaints on this project
0
Complaints against the builder
0
Often reported per project on MahaRERA
No complaints found in the data we have. This isn't a guarantee — verify on the portal.
Extension history
Each time the completion deadline was officially pushed back.
| From | Extended to | Reason |
|---|---|---|
| 28 Aug 2022 | 28 Apr 2025 | MahaRERA extension (original vs revised completion date) |