Nirman Villa

P52000004453

Raigarh, MaharashtraResidential / Group HousingOverdue

Behind schedule

This project is about 48 months past its latest deadline and is not yet marked completed.

Where this project stands

The journey from RERA registration to completion, in order.

Registered 9 Aug 2017Due 30 Jun 2022

Past deadline by ~48 months.

  1. Registered with RERA

    9 Aug 2017
  2. Original promised completion

    30 Dec 2019

    The deadline the builder committed to at registration.

  3. Revised deadline after extensions

    30 Jun 2022

    Pushed back ~30 months across 1 extension.

  4. Today — still not completed

    About 48 months past the latest deadline.

Timeline & delay

Key dates and how they compare to what was promised.

9 Aug 2017

When the project was registered with RERA.

30 Dec 2019

The deadline committed to at registration.

30 Jun 2022

After all approved extensions.

Handover date, when available.

48 mo overdue47.7 mo

How far past deadline an ongoing project is.

1

More extensions can signal execution risk.

On MahaRERA this project's registration status is Ongoing and its completion status is Lapsed. “Registration status” is the legal state of the filing; “completion status” is how far along construction is.

Complaints

Buyer complaints recorded on the official registry.

Complaints on this project

0

Complaints against the builder

0

Often reported per project on MahaRERA

No complaints found in the data we have. This isn't a guarantee — verify on the portal.

Extension history

Each time the completion deadline was officially pushed back.

FromExtended toReason
30 Dec 201930 Jun 2022MahaRERA extension (original vs revised completion date)

About the builder

How this developer has performed across all their tracked projects.

Poor track record

Tracking 1 project — 0 delivered, 1 still active. 1 of 1 (100%) ran late. Limited history — read the project list before drawing conclusions.

1 projects1 delayed (100%)

See NIRMAN ENTERPRISES's full track record →

Official records

View this project on the MahaRERA portal

Builder: NIRMAN ENTERPRISES (NAME:NIRMAN ENTERPRISES)