SWAGAT VILLAGE

P52000005559

Raigarh, MaharashtraResidential / Group HousingIn progress

Under construction

Currently within its planned build window. Watch the deadline and any new extensions.

Where this project stands

The journey from RERA registration to completion, in order.

Registered 11 Aug 2017Due 29 Jun 2027

Approaching the deadline.

  1. Registered with RERA

    11 Aug 2017
  2. Original promised completion

    30 Jun 2023

    The deadline the builder committed to at registration.

  3. Revised deadline after extensions

    29 Jun 2027

    Pushed back ~48 months across 1 extension.

  4. Today — in progress

    About 12 months left until the deadline.

Timeline & delay

Key dates and how they compare to what was promised.

11 Aug 2017

When the project was registered with RERA.

30 Jun 2023

The deadline committed to at registration.

29 Jun 2027

After all approved extensions.

Handover date, when available.

On track0 mo

How far past deadline an ongoing project is.

1

More extensions can signal execution risk.

On MahaRERA this project's registration status is Ongoing and its completion status is Active. “Registration status” is the legal state of the filing; “completion status” is how far along construction is.

Complaints

Buyer complaints recorded on the official registry.

Complaints on this project

0

Complaints against the builder

0

Often reported per project on MahaRERA

No complaints found in the data we have. This isn't a guarantee — verify on the portal.

Extension history

Each time the completion deadline was officially pushed back.

FromExtended toReason
30 Jun 202329 Jun 2027MahaRERA extension (original vs revised completion date)

About the builder

How this developer has performed across all their tracked projects.

Strong track record

Tracking 1 project — 0 delivered, 1 still active. Limited history — read the project list before drawing conclusions.

1 projects0 delayed (0%)

See NAYAN INFRASTRUCTURE's full track record →

Official records

View this project on the MahaRERA portal

Builder: NAYAN INFRASTRUCTURE (NAME:NAYAN INFRASTRUCTURE)

Data last refreshed 21 Jun 2026.