VIVIANA - BLOCK 2
P52000012071
Behind schedule
This project is about 6 months past its latest deadline and is not yet marked completed.
Where this project stands
The journey from RERA registration to completion, in order.
Past deadline by ~6 months.
Registered with RERA
1 Sept 2017Original promised completion
30 Dec 2025The deadline the builder committed to at registration.
Today — still not completed
About 6 months past the latest deadline.
Timeline & delay
Key dates and how they compare to what was promised.
1 Sept 2017
When the project was registered with RERA.
30 Dec 2025
The deadline committed to at registration.
30 Dec 2025
After all approved extensions.
—
Handover date, when available.
6 mo overdue5.7 mo
How far past deadline an ongoing project is.
0
More extensions can signal execution risk.
Complaints
Buyer complaints recorded on the official registry.
Complaints on this project
0
Complaints against the builder
0
Often reported per project on MahaRERA
No complaints found in the data we have. This isn't a guarantee — verify on the portal.
About the builder
How this developer has performed across all their tracked projects.
Strong track record
Tracking 6 projects — 3 delivered, 3 still active. 2 of 6 (33%) ran late.
See NIRMAN REALTORS AND DEVELOPERS LTD's full track record →
Official records
Builder: NIRMAN REALTORS AND DEVELOPERS LTD (NAME:NIRMAN REALTORS AND DEVELOPERS LTD)
Data last refreshed 21 Jun 2026.