Amanora Gateway Tower 100

P52100000380

Pune, MaharashtraResidential / Group HousingCompleted

Delivered — but late

This project was completed about 24 months after its original promised deadline.

Where this project stands

The journey from RERA registration to completion, in order.

Registered 15 Jul 2017Due 29 Apr 2022

Completed.

  1. Registered with RERA

    15 Jul 2017
  2. Original promised completion

    30 Apr 2020

    The deadline the builder committed to at registration.

  3. Revised deadline after extensions

    29 Apr 2022

    Pushed back ~24 months across 1 extension.

  4. Marked completed on the portal

    Shown as completed on the official registry (no exact date scraped).

Timeline & delay

Key dates and how they compare to what was promised.

15 Jul 2017

When the project was registered with RERA.

30 Apr 2020

The deadline committed to at registration.

29 Apr 2022

After all approved extensions.

Handover date, when available.

24 mo delay24 mo

How late the finished project was.

1

More extensions can signal execution risk.

On MahaRERA this project's registration status is Ongoing and its completion status is Completed. “Registration status” is the legal state of the filing; “completion status” is how far along construction is.

Complaints

Buyer complaints recorded on the official registry.

Complaints on this project

0

Complaints against the builder

0

Often reported per project on MahaRERA

No complaints found in the data we have. This isn't a guarantee — verify on the portal.

Extension history

Each time the completion deadline was officially pushed back.

FromExtended toReason
30 Apr 202029 Apr 2022MahaRERA extension (original vs revised completion date)

About the builder

How this developer has performed across all their tracked projects.

Weak track record

Tracking 2 projects — 2 delivered, 0 still active. 1 of 2 (50%) ran late by an average of 12 months. Limited history — read the project list before drawing conclusions.

2 projects1 delayed (50%)50% on time

See City Corporation Limited's full track record →

Official records

View this project on the MahaRERA portal

Builder: City Corporation Limited (NAME:CITY)

Data last refreshed 23 Jun 2026.