← Back to search

Saloni

P52100003071

Pune, MaharashtraResidential / Group HousingCompleted

Delivered — but late

This project was completed about 17 months after its original promised deadline.

Where this project stands

The journey from RERA registration to completion, in order.

Registered 4 Aug 2017Due 31 Dec 2019

Completed.

  1. Registered with RERA

    4 Aug 2017
  2. Original promised completion

    31 Jul 2018

    The deadline the builder committed to at registration.

  3. Revised deadline after extensions

    31 Dec 2019

    Pushed back ~17 months across 1 extension.

  4. Marked completed on the portal

    Shown as completed on the official registry (no exact date scraped).

Timeline & delay

Key dates and how they compare to what was promised.

4 Aug 2017

When the project was registered with RERA.

31 Jul 2018

The deadline committed to at registration.

31 Dec 2019

After all approved extensions.

Handover date, when available.

17 mo delay17 mo

How late the finished project was.

1

More extensions can signal execution risk.

On MahaRERA this project's registration status is Ongoing and its completion status is Completed. “Registration status” is the legal state of the filing; “completion status” is how far along construction is.

Complaints

Buyer complaints recorded on the official registry.

Complaints on this project

0

Complaints against the builder

0

Often reported per project on MahaRERA

No complaints found in the data we have. This isn't a guarantee — verify on the portal.

Extension history

Each time the completion deadline was officially pushed back.

FromExtended toReason
31 Jul 201831 Dec 2019MahaRERA extension (original vs revised completion date)

About the builder

How this developer has performed across all their tracked projects.

Poor track record

Tracking 4 projects — 4 delivered, 0 still active. 3 of 4 (75%) ran late by an average of 13 months.

4 projects3 delayed (75%)25% on time

See Gokhale Constructions's full track record →

Official records

View this project on the MahaRERA portal

Builder: Gokhale Constructions (NAME:GOKHALE CONSTRUCTIONS)

Data last refreshed 24 Jun 2026.