GREYSTONE PARK

P52100010640

Pune, MaharashtraResidential / Group HousingOverdue

Behind schedule

This project is about 100 months past its latest deadline and is not yet marked completed.

Where this project stands

The journey from RERA registration to completion, in order.

Registered 31 Aug 2017Due 12 Feb 2018

Past deadline by ~100 months.

  1. Registered with RERA

    31 Aug 2017
  2. Original promised completion

    12 Feb 2018

    The deadline the builder committed to at registration.

  3. Today — still not completed

    About 100 months past the latest deadline.

Timeline & delay

Key dates and how they compare to what was promised.

31 Aug 2017

When the project was registered with RERA.

12 Feb 2018

The deadline committed to at registration.

12 Feb 2018

After all approved extensions.

Handover date, when available.

100 mo overdue100.4 mo

How far past deadline an ongoing project is.

0

More extensions can signal execution risk.

On MahaRERA this project's registration status is Ongoing and its completion status is Lapsed. “Registration status” is the legal state of the filing; “completion status” is how far along construction is.

Complaints

Buyer complaints recorded on the official registry.

Complaints on this project

0

Complaints against the builder

0

Often reported per project on MahaRERA

No complaints found in the data we have. This isn't a guarantee — verify on the portal.

About the builder

How this developer has performed across all their tracked projects.

Poor track record

Tracking 1 project — 0 delivered, 1 still active. 1 of 1 (100%) ran late. Limited history — read the project list before drawing conclusions.

1 projects1 delayed (100%)

See SIDDHESHWAR CONSTRUCTION's full track record →

Official records

View this project on the MahaRERA portal

Builder: SIDDHESHWAR CONSTRUCTION (NAME:SIDDHESHWAR CONSTRUCTION)

Data last refreshed 24 Jun 2026.