Geras Isle Royale Tower 4 and 5
P52100011031
Under construction
Currently within its planned build window. Watch the deadline and any new extensions.
Where this project stands
The journey from RERA registration to completion, in order.
Approaching the deadline.
Registered with RERA
31 Aug 2017Original promised completion
30 Apr 2024The deadline the builder committed to at registration.
Revised deadline after extensions
30 Apr 2027Pushed back ~36 months across 1 extension.
Today — in progress
About 10 months left until the deadline.
Timeline & delay
Key dates and how they compare to what was promised.
31 Aug 2017
When the project was registered with RERA.
30 Apr 2024
The deadline committed to at registration.
30 Apr 2027
After all approved extensions.
—
Handover date, when available.
On track0 mo
How far past deadline an ongoing project is.
1
More extensions can signal execution risk.
Complaints
Buyer complaints recorded on the official registry.
Complaints on this project
0
Complaints against the builder
0
Often reported per project on MahaRERA
No complaints found in the data we have. This isn't a guarantee — verify on the portal.
Extension history
Each time the completion deadline was officially pushed back.
| From | Extended to | Reason |
|---|---|---|
| 30 Apr 2024 | 30 Apr 2027 | MahaRERA extension (original vs revised completion date) |
About the builder
How this developer has performed across all their tracked projects.
Mixed track record
Tracking 7 projects — 4 delivered, 3 still active. 2 of 7 (29%) ran late by an average of 4 months.
Official records
Builder: Gera Developments Private Limited (NAME:GERA DEVELOPMENTS)
Data last refreshed 24 Jun 2026.