GRAND ORCHID
P52100011707
Behind schedule
This project is about 64 months past its latest deadline and is not yet marked completed.
Where this project stands
The journey from RERA registration to completion, in order.
Past deadline by ~64 months.
Registered with RERA
31 Aug 2017Original promised completion
1 Sept 2019The deadline the builder committed to at registration.
Revised deadline after extensions
28 Feb 2021Pushed back ~18 months across 1 extension.
Today — still not completed
About 64 months past the latest deadline.
Timeline & delay
Key dates and how they compare to what was promised.
31 Aug 2017
When the project was registered with RERA.
1 Sept 2019
The deadline committed to at registration.
28 Feb 2021
After all approved extensions.
—
Handover date, when available.
64 mo overdue63.9 mo
How far past deadline an ongoing project is.
1
More extensions can signal execution risk.
Complaints
Buyer complaints recorded on the official registry.
Complaints on this project
0
Complaints against the builder
0
Often reported per project on MahaRERA
No complaints found in the data we have. This isn't a guarantee — verify on the portal.
Extension history
Each time the completion deadline was officially pushed back.
| From | Extended to | Reason |
|---|---|---|
| 1 Sept 2019 | 28 Feb 2021 | MahaRERA extension (original vs revised completion date) |
About the builder
How this developer has performed across all their tracked projects.
Poor track record
Tracking 2 projects — 0 delivered, 2 still active. 2 of 2 (100%) ran late. Limited history — read the project list before drawing conclusions.
See SHREE SIDDHIVINAYAK CONSTRUCTION GROUP's full track record →
Official records
Builder: SHREE SIDDHIVINAYAK CONSTRUCTION GROUP (NAME:SHREE SIDDHIVINAYAK CONSTRUCTION GROUP)
Data last refreshed 24 Jun 2026.