ANTRIKSH GOLF LINKS (PHASE-1)
UPRERAPRJ10360
Delivered — but late
This project was completed about 6 months after its original promised deadline.
Where this project stands
The journey from RERA registration to completion, in order.
Completed.
Registered with RERA
13 Aug 2017Original promised completion
19 Feb 2021The deadline the builder committed to at registration.
Revised deadline after extensions
18 Aug 2021Pushed back ~6 months across 1 extension.
Marked completed on the portal
Shown as completed on the official registry (no exact date scraped).
Timeline & delay
Key dates and how they compare to what was promised.
13 Aug 2017
When the project was registered with RERA.
19 Feb 2021
The deadline committed to at registration.
18 Aug 2021
After all approved extensions.
—
Handover date, when available.
6 mo delay6 mo
How late the finished project was.
1
More extensions can signal execution risk.
Complaints
Buyer complaints recorded on the official registry.
Complaints on this project
0
Complaints against the builder
0
No complaints found in the data we have. This isn't a guarantee — verify on the portal.
Extension history
Each time the completion deadline was officially pushed back.
| From | Extended to | Reason |
|---|---|---|
| 19 Feb 2021 | 18 Aug 2021 | 18-08-2021 (Six months extension in view of force majeure caused by covid-19 pandemic) |
About the builder
How this developer has performed across all their tracked projects.
Poor track record
Tracking 4 projects — 4 delivered, 0 still active. 4 of 4 (100%) ran late by an average of 6 months.
See M/S ANTRIKSH ENGINEERS PRIVATE LIMITED ( ANTRIKSH's full track record →
Official records
Builder: M/S ANTRIKSH ENGINEERS PRIVATE LIMITED ( ANTRIKSH (NAME:M/S ANTRIKSH ENGINEERS PRIVATE LIMITED ( ANTRIKSH)
Data last refreshed 21 Jun 2026.