← Back to search

PLOT ZONE V (1B)

UPRERAPRJ10825

Uttar PradeshCompleted

Delivered — but late

This project was completed about 6 months after its original promised deadline.

Where this project stands

The journey from RERA registration to completion, in order.

Registered 14 Aug 2017Due 14 Feb 2026

Completed.

  1. Registered with RERA

    14 Aug 2017
  2. Original promised completion

    15 Aug 2025

    The deadline the builder committed to at registration.

  3. Revised deadline after extensions

    14 Feb 2026

    Pushed back ~6 months across 1 extension.

  4. Marked completed on the portal

    Shown as completed on the official registry (no exact date scraped).

Timeline & delay

Key dates and how they compare to what was promised.

14 Aug 2017

When the project was registered with RERA.

15 Aug 2025

The deadline committed to at registration.

14 Feb 2026

After all approved extensions.

Handover date, when available.

6 mo delay6 mo

How late the finished project was.

1

More extensions can signal execution risk.

On UP RERA this project's registration status is Completed. “Registration status” is the legal state of the filing; “completion status” is how far along construction is.

Complaints

Buyer complaints recorded on the official registry.

Complaints on this project

0

Complaints against the builder

0

No complaints found in the data we have. This isn't a guarantee — verify on the portal.

Extension history

Each time the completion deadline was officially pushed back.

FromExtended toReason
15 Aug 202514 Feb 202614-02-2026 (Six months extension in view of force majeure caused by covid-19 pandemic)

About the builder

How this developer has performed across all their tracked projects.

Poor track record

Tracking 25 projects — 11 delivered, 14 still active. 23 of 25 (92%) ran late by an average of 5 months.

25 projects23 delayed (92%)18% on time

See M/S UTTAM STEELS & ASSOCIATES { CONSORTIUM) THROUG's full track record →

Official records

View this project on the UP RERA portal

Builder: M/S UTTAM STEELS & ASSOCIATES { CONSORTIUM) THROUG (NAME:M/S UTTAM STEELS & ASSOCIATES { CONSORTIUM) THROUG)

Data last refreshed 21 Jun 2026.