PRESITHUM-PRESIDENCY HEIGHTS (Ph-I)

RERA project status · delays · complaints

UPRERAPRJ10984

Uttar PradeshCompleted

Delivered — but late

This project was completed about 18 months after its original promised deadline.

Where this project stands

The journey from RERA registration to completion, in order.

Registered 14 Aug 2017Due 28 Sept 2022

Completed.

  1. Registered with RERA

    14 Aug 2017
  2. Original promised completion

    31 Mar 2021

    The deadline the builder committed to at registration.

  3. Revised deadline after extensions

    28 Sept 2022

    Pushed back ~18 months across 2 extensions.

  4. Marked completed on the portal

    Shown as completed on the official registry (no exact date scraped).

Timeline & delay

Key dates and how they compare to what was promised.

14 Aug 2017

When the project was registered with RERA.

31 Mar 2021

The deadline committed to at registration.

28 Sept 2022

After all approved extensions.

Handover date, when available.

18 mo delay17.9 mo

How late the finished project was.

2

More extensions can signal execution risk.

On UP RERA this project's registration status is Completed. “Registration status” is the legal state of the filing; “completion status” is how far along construction is.

Complaints

Buyer complaints recorded on the official registry.

Complaints on this project

0

Complaints against the builder

0

No complaints found in the data we have. This isn't a guarantee — verify on the portal.

Extension history

Each time the completion deadline was officially pushed back.

FromExtended toReason
31 Mar 202129 Sept 202129-09-2021 (Six months extension in view of force majeure caused by covid-19 pandemic)
29 Sept 202128 Sept 2022

Official records

View this project on the UP RERA portal

Data last refreshed 21 Jun 2026.