GLORY 46 (PHASE-5)

RERA project status · delays · complaints

UPRERAPRJ11614

Uttar PradeshCompleted

Delivered — but late

This project was completed about 6 months after its original promised deadline.

Where this project stands

The journey from RERA registration to completion, in order.

Registered 15 Aug 2017Due 14 Apr 2021

Completed.

  1. Registered with RERA

    15 Aug 2017
  2. Original promised completion

    15 Oct 2020

    The deadline the builder committed to at registration.

  3. Revised deadline after extensions

    14 Apr 2021

    Pushed back ~6 months across 1 extension.

  4. Marked completed on the portal

    Shown as completed on the official registry (no exact date scraped).

Timeline & delay

Key dates and how they compare to what was promised.

15 Aug 2017

When the project was registered with RERA.

15 Oct 2020

The deadline committed to at registration.

14 Apr 2021

After all approved extensions.

Handover date, when available.

6 mo delay6 mo

How late the finished project was.

1

More extensions can signal execution risk.

On UP RERA this project's registration status is Completed. “Registration status” is the legal state of the filing; “completion status” is how far along construction is.

Complaints

Buyer complaints recorded on the official registry.

Complaints on this project

0

Complaints against the builder

0

No complaints found in the data we have. This isn't a guarantee — verify on the portal.

Extension history

Each time the completion deadline was officially pushed back.

FromExtended toReason
15 Oct 202014 Apr 202114-04-2021 (Six months extension in view of force majeure caused by covid-19 pandemic)