Curio City

UPRERAPRJ14041

Uttar PradeshCompleted

Delivered — but late

This project was completed about 6 months after its original promised deadline.

Where this project stands

The journey from RERA registration to completion, in order.

Registered 30 Oct 2017Due 30 Jun 2022

Completed.

  1. Registered with RERA

    30 Oct 2017
  2. Original promised completion

    31 Dec 2021

    The deadline the builder committed to at registration.

  3. Revised deadline after extensions

    30 Jun 2022

    Pushed back ~6 months across 1 extension.

  4. Marked completed on the portal

    Shown as completed on the official registry (no exact date scraped).

Timeline & delay

Key dates and how they compare to what was promised.

30 Oct 2017

When the project was registered with RERA.

31 Dec 2021

The deadline committed to at registration.

30 Jun 2022

After all approved extensions.

Handover date, when available.

6 mo delay6 mo

How late the finished project was.

1

More extensions can signal execution risk.

On UP RERA this project's registration status is Completed. “Registration status” is the legal state of the filing; “completion status” is how far along construction is.

Complaints

Buyer complaints recorded on the official registry.

Complaints on this project

0

Complaints against the builder

0

No complaints found in the data we have. This isn't a guarantee — verify on the portal.

Extension history

Each time the completion deadline was officially pushed back.

FromExtended toReason
31 Dec 202130 Jun 202230-06-2022 (Six months extension in view of force majeure caused by covid-19 pandemic)

About the builder

How this developer has performed across all their tracked projects.

Poor track record

Tracking 1 project — 1 delivered, 0 still active. 1 of 1 (100%) ran late by an average of 6 months. Limited history — read the project list before drawing conclusions.

1 projects1 delayed (100%)0% on time

See ORRIS INFRASTRUCTURE PRIVATE LIMITED's full track record →

Official records

View this project on the UP RERA portal

Builder: ORRIS INFRASTRUCTURE PRIVATE LIMITED (NAME:ORRIS INFRASTRUCTURE PRIVATE LIMITED)