Galactic City-Universal Tower
RERA project status · delays · complaints
UPRERAPRJ15254
Under construction
Currently within its planned build window. Watch the deadline and any new extensions.
Where this project stands
The journey from RERA registration to completion, in order.
Approaching the deadline.
Registered with RERA
21 Feb 2018Original promised completion
28 Feb 2022The deadline the builder committed to at registration.
Revised deadline after extensions
31 Dec 2027Pushed back ~70 months across 2 extensions.
Today — in progress
About 17 months left until the deadline.
Timeline & delay
Key dates and how they compare to what was promised.
21 Feb 2018
When the project was registered with RERA.
28 Feb 2022
The deadline committed to at registration.
31 Dec 2027
After all approved extensions.
—
Handover date, when available.
On track0 mo
How far past deadline an ongoing project is.
2
More extensions can signal execution risk.
Complaints
Buyer complaints recorded on the official registry.
Complaints on this project
0
Complaints against the builder
0
No complaints found in the data we have. This isn't a guarantee — verify on the portal.
Extension history
Each time the completion deadline was officially pushed back.
| From | Extended to | Reason |
|---|---|---|
| 28 Feb 2022 | 27 Aug 2022 | 27-08-2022 (Six months extension in view of force majeure caused by covid-19 pandemic) |
| 27 Aug 2022 | 31 Dec 2027 | — |
Official records
Data last refreshed 20 Jun 2026.