HAPPY TRAILS
UPRERAPRJ15574
Behind schedule
This project is about 8 months past its latest deadline and is not yet marked completed.
Where this project stands
The journey from RERA registration to completion, in order.
Past deadline by ~8 months.
Registered with RERA
29 Mar 2018Original promised completion
30 Apr 2025The deadline the builder committed to at registration.
Revised deadline after extensions
29 Oct 2025Pushed back ~6 months across 1 extension.
Today — still not completed
About 8 months past the latest deadline.
Timeline & delay
Key dates and how they compare to what was promised.
29 Mar 2018
When the project was registered with RERA.
30 Apr 2025
The deadline committed to at registration.
29 Oct 2025
After all approved extensions.
—
Handover date, when available.
8 mo overdue7.8 mo
How far past deadline an ongoing project is.
1
More extensions can signal execution risk.
Complaints
Buyer complaints recorded on the official registry.
Complaints on this project
0
Complaints against the builder
0
No complaints found in the data we have. This isn't a guarantee — verify on the portal.
Extension history
Each time the completion deadline was officially pushed back.
| From | Extended to | Reason |
|---|---|---|
| 30 Apr 2025 | 29 Oct 2025 | 29-10-2025 (Six months extension in view of force majeure caused by covid-19 pandemic) |
About the builder
How this developer has performed across all their tracked projects.
Poor track record
Tracking 1 project — 0 delivered, 1 still active. 1 of 1 (100%) ran late. Limited history — read the project list before drawing conclusions.
See SHRIDHARA INFRATECH PRIVATE LIMITED's full track record →
Official records
Builder: SHRIDHARA INFRATECH PRIVATE LIMITED (UPRERAPRM40553)
Data last refreshed 20 Jun 2026.