BOULEVARD WALK (PHASE 4)
UPRERAPRJ15654
Behind schedule
This project is about 39 months past its latest deadline and is not yet marked completed.
Where this project stands
The journey from RERA registration to completion, in order.
Past deadline by ~39 months.
Registered with RERA
10 Apr 2018Original promised completion
31 Dec 2020The deadline the builder committed to at registration.
Revised deadline after extensions
29 Mar 2023Pushed back ~27 months across 2 extensions.
Today — still not completed
About 39 months past the latest deadline.
Timeline & delay
Key dates and how they compare to what was promised.
10 Apr 2018
When the project was registered with RERA.
31 Dec 2020
The deadline committed to at registration.
29 Mar 2023
After all approved extensions.
—
Handover date, when available.
39 mo overdue38.8 mo
How far past deadline an ongoing project is.
2
More extensions can signal execution risk.
Complaints
Buyer complaints recorded on the official registry.
Complaints on this project
0
Complaints against the builder
0
No complaints found in the data we have. This isn't a guarantee — verify on the portal.
Extension history
Each time the completion deadline was officially pushed back.
| From | Extended to | Reason |
|---|---|---|
| 31 Dec 2020 | 30 Jun 2021 | 30-06-2021 (Six months extension in view of force majeure caused by covid-19 pandemic) |
| 30 Jun 2021 | 29 Mar 2023 | — |
About the builder
How this developer has performed across all their tracked projects.
Poor track record
Tracking 4 projects — 0 delivered, 4 still active. 4 of 4 (100%) ran late.
See REGAL EMPORIA INFRATECH PRIVATE LIMITED's full track record →
Official records
Builder: REGAL EMPORIA INFRATECH PRIVATE LIMITED (NAME:REGAL EMPORIA INFRATECH PRIVATE LIMITED)
Data last refreshed 20 Jun 2026.