Unibera Elite 70
UPRERAPRJ15830
Behind schedule
This project is about 53 months past its latest deadline and is not yet marked completed.
Where this project stands
The journey from RERA registration to completion, in order.
Past deadline by ~53 months.
Registered with RERA
24 Apr 2018Original promised completion
31 Jul 2021The deadline the builder committed to at registration.
Revised deadline after extensions
30 Jan 2022Pushed back ~6 months across 1 extension.
Today — still not completed
About 53 months past the latest deadline.
Timeline & delay
Key dates and how they compare to what was promised.
24 Apr 2018
When the project was registered with RERA.
31 Jul 2021
The deadline committed to at registration.
30 Jan 2022
After all approved extensions.
—
Handover date, when available.
53 mo overdue52.7 mo
How far past deadline an ongoing project is.
1
More extensions can signal execution risk.
Complaints
Buyer complaints recorded on the official registry.
Complaints on this project
0
Complaints against the builder
0
No complaints found in the data we have. This isn't a guarantee — verify on the portal.
Extension history
Each time the completion deadline was officially pushed back.
| From | Extended to | Reason |
|---|---|---|
| 31 Jul 2021 | 30 Jan 2022 | 30-01-2022 (Six months extension in view of force majeure caused by covid-19 pandemic) |
About the builder
How this developer has performed across all their tracked projects.
Poor track record
Tracking 2 projects — 0 delivered, 2 still active. 2 of 2 (100%) ran late. Limited history — read the project list before drawing conclusions.
Official records
Builder: UNIBERA DEVELOPERS PVT LTD (NAME:UNIBERA DEVELOPERS PVT LTD)
Data last refreshed 20 Jun 2026.