Jaypee Greens, V-04 Land 2, Greater Noida
UPRERAPRJ15897
Behind schedule
This project is about 56 months past its latest deadline and is not yet marked completed.
Where this project stands
The journey from RERA registration to completion, in order.
Past deadline by ~56 months.
Registered with RERA
28 Apr 2018Original promised completion
27 Apr 2021The deadline the builder committed to at registration.
Revised deadline after extensions
26 Oct 2021Pushed back ~6 months across 1 extension.
Today — still not completed
About 56 months past the latest deadline.
Timeline & delay
Key dates and how they compare to what was promised.
28 Apr 2018
When the project was registered with RERA.
27 Apr 2021
The deadline committed to at registration.
26 Oct 2021
After all approved extensions.
—
Handover date, when available.
56 mo overdue55.9 mo
How far past deadline an ongoing project is.
1
More extensions can signal execution risk.
Complaints
Buyer complaints recorded on the official registry.
Complaints on this project
0
Complaints against the builder
0
No complaints found in the data we have. This isn't a guarantee — verify on the portal.
Extension history
Each time the completion deadline was officially pushed back.
| From | Extended to | Reason |
|---|---|---|
| 27 Apr 2021 | 26 Oct 2021 | 26-10-2021 (Six months extension in view of force majeure caused by covid-19 pandemic) |
About the builder
How this developer has performed across all their tracked projects.
Poor track record
Tracking 35 projects — 21 delivered, 14 still active. 25 of 35 (71%) ran late by an average of 5 months.
Official records
Builder: JAIPRAKASH ASSOCIATES LIMITED (NAME:JAIPRAKASH ASSOCIATES LIMITED)
Data last refreshed 20 Jun 2026.