3rd PARK VIEW - GAUR YAMUNA CITY
UPRERAPRJ16103
Behind schedule
This project is about 32 months past its latest deadline and is not yet marked completed.
Where this project stands
The journey from RERA registration to completion, in order.
Past deadline by ~32 months.
Registered with RERA
18 May 2018Original promised completion
9 Apr 2023The deadline the builder committed to at registration.
Revised deadline after extensions
8 Oct 2023Pushed back ~6 months across 1 extension.
Today — still not completed
About 32 months past the latest deadline.
Timeline & delay
Key dates and how they compare to what was promised.
18 May 2018
When the project was registered with RERA.
9 Apr 2023
The deadline committed to at registration.
8 Oct 2023
After all approved extensions.
—
Handover date, when available.
32 mo overdue32.4 mo
How far past deadline an ongoing project is.
1
More extensions can signal execution risk.
Complaints
Buyer complaints recorded on the official registry.
Complaints on this project
0
Complaints against the builder
0
No complaints found in the data we have. This isn't a guarantee — verify on the portal.
Extension history
Each time the completion deadline was officially pushed back.
| From | Extended to | Reason |
|---|---|---|
| 9 Apr 2023 | 8 Oct 2023 | 08-10-2023 (Six months extension in view of force majeure caused by covid-19 pandemic) |
About the builder
How this developer has performed across all their tracked projects.
Poor track record
Tracking 4 projects — 0 delivered, 4 still active. 4 of 4 (100%) ran late.
Official records
Builder: GAURSONS REALTECH PRIVATE LIMITED (UPRERAPRM1654)
Data last refreshed 20 Jun 2026.