Park Lane at Godrej Golf Link
UPRERAPRJ16697
Behind schedule
This project is about 36 months past its latest deadline and is not yet marked completed.
Where this project stands
The journey from RERA registration to completion, in order.
Past deadline by ~36 months.
Registered with RERA
29 Jun 2018Original promised completion
15 Dec 2021The deadline the builder committed to at registration.
Revised deadline after extensions
13 Jun 2023Pushed back ~18 months across 2 extensions.
Today — still not completed
About 36 months past the latest deadline.
Timeline & delay
Key dates and how they compare to what was promised.
29 Jun 2018
When the project was registered with RERA.
15 Dec 2021
The deadline committed to at registration.
13 Jun 2023
After all approved extensions.
—
Handover date, when available.
36 mo overdue36.3 mo
How far past deadline an ongoing project is.
2
More extensions can signal execution risk.
Complaints
Buyer complaints recorded on the official registry.
Complaints on this project
0
Complaints against the builder
0
No complaints found in the data we have. This isn't a guarantee — verify on the portal.
Extension history
Each time the completion deadline was officially pushed back.
| From | Extended to | Reason |
|---|---|---|
| 15 Dec 2021 | 14 Jun 2022 | 14-06-2022 (Six months extension in view of force majeure caused by covid-19 pandemic) |
| 14 Jun 2022 | 13 Jun 2023 | — |
About the builder
How this developer has performed across all their tracked projects.
Poor track record
Tracking 4 projects — 0 delivered, 4 still active. 4 of 4 (100%) ran late.
Official records
Builder: AR LANDCRAFT LLP (UPRERAPRM1081)
Data last refreshed 20 Jun 2026.