Hi Castle

RERA project status · delays · complaints

UPRERAPRJ17726

Uttar PradeshCompleted

Delivered — but late

This project was completed about 21 months after its original promised deadline.

Where this project stands

The journey from RERA registration to completion, in order.

Registered 8 Oct 2018Due 30 Jun 2025

Completed.

  1. Registered with RERA

    8 Oct 2018
  2. Original promised completion

    30 Sept 2023

    The deadline the builder committed to at registration.

  3. Revised deadline after extensions

    30 Jun 2025

    Pushed back ~21 months across 3 extensions.

  4. Marked completed on the portal

    Shown as completed on the official registry (no exact date scraped).

Timeline & delay

Key dates and how they compare to what was promised.

8 Oct 2018

When the project was registered with RERA.

30 Sept 2023

The deadline committed to at registration.

30 Jun 2025

After all approved extensions.

—

Handover date, when available.

21 mo delay21 mo

How late the finished project was.

3

More extensions can signal execution risk.

On UP RERA this project's registration status is Completed. “Registration status” is the legal state of the filing; “completion status” is how far along construction is.

Complaints

Buyer complaints recorded on the official registry.

Complaints on this project

0

Complaints against the builder

0

No complaints found in the data we have. This isn't a guarantee — verify on the portal.

Extension history

Each time the completion deadline was officially pushed back.

FromExtended toReason
30 Sept 202329 Mar 202429-03-2024 (Six months extension in view of force majeure caused by covid-19 pandemic)
29 Mar 202431 Oct 2024—
31 Oct 202430 Jun 2025—

Official records

View this project on the UP RERA portal

Data last refreshed 21 Jun 2026.