← Back to search

SKA ORION

RERA project status · delays · complaints

UPRERAPRJ186008

Uttar PradeshCompleted

Delivered on time

Marked completed on the registry on or before the promised deadline.

Where this project stands

The journey from RERA registration to completion, in order.

Registered 18 Mar 2021Due 31 Mar 2026

Completed.

  1. Registered with RERA

    18 Mar 2021
  2. Original promised completion

    31 Mar 2026

    The deadline the builder committed to at registration.

  3. Marked completed on the portal

    Shown as completed on the official registry (no exact date scraped).

Timeline & delay

Key dates and how they compare to what was promised.

18 Mar 2021

When the project was registered with RERA.

31 Mar 2026

The deadline committed to at registration.

31 Mar 2026

After all approved extensions.

Handover date, when available.

On track0 mo

How far past deadline an ongoing project is.

0

More extensions can signal execution risk.

On UP RERA this project's registration status is Completed. “Registration status” is the legal state of the filing; “completion status” is how far along construction is.

Complaints

Buyer complaints recorded on the official registry.

Complaints on this project

0

Complaints against the builder

0

No complaints found in the data we have. This isn't a guarantee — verify on the portal.

Official records

View this project on the UP RERA portal

Data last refreshed 21 Jun 2026.