Mahagun Manorial
UPRERAPRJ2051
Under construction
Currently within its planned build window. Watch the deadline and any new extensions.
Where this project stands
The journey from RERA registration to completion, in order.
Approaching the deadline.
Registered with RERA
27 Jul 2017Original promised completion
31 Dec 2021The deadline the builder committed to at registration.
Revised deadline after extensions
30 Jun 2027Pushed back ~66 months across 3 extensions.
Today — in progress
About 12 months left until the deadline.
Timeline & delay
Key dates and how they compare to what was promised.
27 Jul 2017
When the project was registered with RERA.
31 Dec 2021
The deadline committed to at registration.
30 Jun 2027
After all approved extensions.
—
Handover date, when available.
On track0 mo
How far past deadline an ongoing project is.
3
More extensions can signal execution risk.
Complaints
Buyer complaints recorded on the official registry.
Complaints on this project
0
Complaints against the builder
0
No complaints found in the data we have. This isn't a guarantee — verify on the portal.
Extension history
Each time the completion deadline was officially pushed back.
| From | Extended to | Reason |
|---|---|---|
| 31 Dec 2021 | 30 Jun 2022 | 30-06-2022 (Six months extension in view of force majeure caused by covid-19 pandemic) |
| 30 Jun 2022 | 29 Mar 2024 | — |
| 29 Mar 2024 | 30 Jun 2027 | — |
About the builder
How this developer has performed across all their tracked projects.
Weak track record
Tracking 2 projects — 0 delivered, 2 still active. 1 of 2 (50%) ran late. Limited history — read the project list before drawing conclusions.
Official records
Builder: MAHAGUN (INDIA) PVT. LTD. (NAME:MAHAGUN (INDIA) PVT. LTD.)
Data last refreshed 20 Jun 2026.