CYBERTHUM PHASE A
UPRERAPRJ236478
Behind schedule
This project is about 16 months past its latest deadline and is not yet marked completed.
Where this project stands
The journey from RERA registration to completion, in order.
Past deadline by ~16 months.
Registered with RERA
5 Feb 2019Original promised completion
1 Dec 2022The deadline the builder committed to at registration.
Revised deadline after extensions
25 Feb 2025Pushed back ~27 months across 3 extensions.
Today — still not completed
About 16 months past the latest deadline.
Timeline & delay
Key dates and how they compare to what was promised.
5 Feb 2019
When the project was registered with RERA.
1 Dec 2022
The deadline committed to at registration.
25 Feb 2025
After all approved extensions.
—
Handover date, when available.
16 mo overdue15.9 mo
How far past deadline an ongoing project is.
3
More extensions can signal execution risk.
Complaints
Buyer complaints recorded on the official registry.
Complaints on this project
0
Complaints against the builder
0
No complaints found in the data we have. This isn't a guarantee — verify on the portal.
Extension history
Each time the completion deadline was officially pushed back.
| From | Extended to | Reason |
|---|---|---|
| 1 Dec 2022 | 30 May 2023 | 30-05-2023 (Six months extension in view of force majeure caused by covid-19 pandemic) |
| 30 May 2023 | 25 Dec 2023 | — |
| 25 Dec 2023 | 25 Feb 2025 | — |
About the builder
How this developer has performed across all their tracked projects.
Poor track record
Tracking 2 projects — 0 delivered, 2 still active. 2 of 2 (100%) ran late. Limited history — read the project list before drawing conclusions.