Gautam Buddha Nagar, Uttar PradeshOngoingOverdue

Behind schedule

This project is about 40 months past its latest deadline and is not yet marked completed.

Where this project stands

The journey from RERA registration to completion, in order.

Registered 27 Jul 2017Due 27 Feb 2023

Past deadline by ~40 months.

  1. Registered with RERA

    27 Jul 2017
  2. Original promised completion

    31 Aug 2022

    The deadline the builder committed to at registration.

  3. Revised deadline after extensions

    27 Feb 2023

    Pushed back ~6 months across 1 extension.

  4. Today — still not completed

    About 40 months past the latest deadline.

Timeline & delay

Key dates and how they compare to what was promised.

27 Jul 2017

When the project was registered with RERA.

31 Aug 2022

The deadline committed to at registration.

27 Feb 2023

After all approved extensions.

Handover date, when available.

40 mo overdue39.8 mo

How far past deadline an ongoing project is.

1

More extensions can signal execution risk.

On UP RERA this project's registration status is Registered. “Registration status” is the legal state of the filing; “completion status” is how far along construction is.

Complaints

Buyer complaints recorded on the official registry.

Complaints on this project

0

Complaints against the builder

0

No complaints found in the data we have. This isn't a guarantee — verify on the portal.

Extension history

Each time the completion deadline was officially pushed back.

FromExtended toReason
31 Aug 202227 Feb 202327-02-2023 (Six months extension in view of force majeure caused by covid-19 pandemic)

About the builder

How this developer has performed across all their tracked projects.

Poor track record

Tracking 1 project — 0 delivered, 1 still active. 1 of 1 (100%) ran late. Limited history — read the project list before drawing conclusions.

1 projects1 delayed (100%)

See IV COUNTY PVT LTD's full track record →

Official records

View this project on the UP RERA portal

Builder: IV COUNTY PVT LTD (UPRERAPRM1792)

Data last refreshed 20 Jun 2026.