Pebble Court

RERA project status · delays · complaints

UPRERAPRJ2623

Gautam Buddha Nagar, Uttar PradeshOngoingOverdue

Behind schedule

This project is past its latest deadline and is not yet marked completed.

Where this project stands

The journey from RERA registration to completion, in order.

Registered 28 Jul 2017Due 18 Jul 2026

Past deadline by ~1 month.

  1. Registered with RERA

    28 Jul 2017
  2. Original promised completion

    31 Mar 2019

    The deadline the builder committed to at registration.

  3. Revised deadline after extensions

    18 Jul 2026

    Pushed back ~88 months across 1 extension.

  4. Today — still not completed

    About 1 month past the latest deadline.

Timeline & delay

Key dates and how they compare to what was promised.

28 Jul 2017

When the project was registered with RERA.

31 Mar 2019

The deadline committed to at registration.

18 Jul 2026

After all approved extensions.

Handover date, when available.

On track0 mo

How far past deadline an ongoing project is.

1

More extensions can signal execution risk.

On UP RERA this project's registration status is Registered. “Registration status” is the legal state of the filing; “completion status” is how far along construction is.

Complaints

Buyer complaints recorded on the official registry.

Complaints on this project

0

Complaints against the builder

0

No complaints found in the data we have. This isn't a guarantee — verify on the portal.

Extension history

Each time the completion deadline was officially pushed back.

FromExtended toReason
31 Mar 201918 Jul 2026

Official records

View this project on the UP RERA portal

Data last refreshed 20 Jun 2026.