Nobility
UPRERAPRJ284035
Under construction
Currently within its planned build window. Watch the deadline and any new extensions.
Where this project stands
The journey from RERA registration to completion, in order.
Approaching the deadline.
Registered with RERA
11 Jun 2019Original promised completion
1 Aug 2026The deadline the builder committed to at registration.
Revised deadline after extensions
31 Jan 2027Pushed back ~6 months across 1 extension.
Today — in progress
About 7 months left until the deadline.
Timeline & delay
Key dates and how they compare to what was promised.
11 Jun 2019
When the project was registered with RERA.
1 Aug 2026
The deadline committed to at registration.
31 Jan 2027
After all approved extensions.
—
Handover date, when available.
On track0 mo
How far past deadline an ongoing project is.
1
More extensions can signal execution risk.
Complaints
Buyer complaints recorded on the official registry.
Complaints on this project
0
Complaints against the builder
0
No complaints found in the data we have. This isn't a guarantee — verify on the portal.
Extension history
Each time the completion deadline was officially pushed back.
| From | Extended to | Reason |
|---|---|---|
| 1 Aug 2026 | 31 Jan 2027 | 31-01-2027 (Six months extension in view of force majeure caused by covid-19 pandemic) |
About the builder
How this developer has performed across all their tracked projects.
Strong track record
Tracking 1 project — 0 delivered, 1 still active. Limited history — read the project list before drawing conclusions.
Official records
Builder: HOMEKRAFT INFRA PRIVATE LIMITED (UPRERAPRM73892)
Data last refreshed 20 Jun 2026.