Festival City Phase-III

RERA project status · delays · complaints

UPRERAPRJ3088

Gautam Buddha Nagar, Uttar PradeshOngoingOverdue

Behind schedule

This project is about 11 months past its latest deadline and is not yet marked completed.

Where this project stands

The journey from RERA registration to completion, in order.

Registered 2 Aug 2017Due 9 Jul 2025

Past deadline by ~13 months.

  1. Registered with RERA

    2 Aug 2017
  2. Original promised completion

    10 Jan 2025

    The deadline the builder committed to at registration.

  3. Revised deadline after extensions

    9 Jul 2025

    Pushed back ~6 months across 1 extension.

  4. Today — still not completed

    About 13 months past the latest deadline.

Timeline & delay

Key dates and how they compare to what was promised.

2 Aug 2017

When the project was registered with RERA.

10 Jan 2025

The deadline committed to at registration.

9 Jul 2025

After all approved extensions.

Handover date, when available.

11 mo overdue11.4 mo

How far past deadline an ongoing project is.

1

More extensions can signal execution risk.

On UP RERA this project's registration status is Registered. “Registration status” is the legal state of the filing; “completion status” is how far along construction is.

Complaints

Buyer complaints recorded on the official registry.

Complaints on this project

0

Complaints against the builder

0

No complaints found in the data we have. This isn't a guarantee — verify on the portal.

Extension history

Each time the completion deadline was officially pushed back.

FromExtended toReason
10 Jan 20259 Jul 202509-07-2025 (Six months extension in view of force majeure caused by covid-19 pandemic)

Official records

View this project on the UP RERA portal