Le Garden (Phase-3, Tower K L M & N)

UPRERAPRJ3852

Uttar PradeshCompleted

Delivered — but late

This project was completed about 53 months after its original promised deadline.

Where this project stands

The journey from RERA registration to completion, in order.

Registered 28 Jul 2017Due 31 May 2025

Completed.

  1. Registered with RERA

    28 Jul 2017
  2. Original promised completion

    31 Dec 2020

    The deadline the builder committed to at registration.

  3. Revised deadline after extensions

    31 May 2025

    Pushed back ~53 months across 3 extensions.

  4. Marked completed on the portal

    Shown as completed on the official registry (no exact date scraped).

Timeline & delay

Key dates and how they compare to what was promised.

28 Jul 2017

When the project was registered with RERA.

31 Dec 2020

The deadline committed to at registration.

31 May 2025

After all approved extensions.

Handover date, when available.

53 mo delay53 mo

How late the finished project was.

3

More extensions can signal execution risk.

On UP RERA this project's registration status is Completed. “Registration status” is the legal state of the filing; “completion status” is how far along construction is.

Complaints

Buyer complaints recorded on the official registry.

Complaints on this project

0

Complaints against the builder

0

No complaints found in the data we have. This isn't a guarantee — verify on the portal.

Extension history

Each time the completion deadline was officially pushed back.

FromExtended toReason
31 Dec 202030 Jun 202130-06-2021 (Six months extension in view of force majeure caused by covid-19 pandemic)
30 Jun 202129 Jun 2022
29 Jun 202231 May 2025

About the builder

How this developer has performed across all their tracked projects.

Poor track record

Tracking 5 projects — 4 delivered, 1 still active. 3 of 5 (60%) ran late by an average of 20 months.

5 projects3 delayed (60%)50% on time

See AJNARA REALTECH LIMITED's full track record →

Official records

View this project on the UP RERA portal

Builder: AJNARA REALTECH LIMITED (NAME:AJNARA REALTECH LIMITED)

Data last refreshed 21 Jun 2026.