BLOSSOM GREENS (PHASE-3 TOWER A , K & CLUB HOUSE)
UPRERAPRJ4218
Behind schedule
This project is about 52 months past its latest deadline and is not yet marked completed.
Where this project stands
The journey from RERA registration to completion, in order.
Past deadline by ~52 months.
Registered with RERA
3 Aug 2017Original promised completion
1 Sept 2021The deadline the builder committed to at registration.
Revised deadline after extensions
28 Feb 2022Pushed back ~6 months across 1 extension.
Today — still not completed
About 52 months past the latest deadline.
Timeline & delay
Key dates and how they compare to what was promised.
3 Aug 2017
When the project was registered with RERA.
1 Sept 2021
The deadline committed to at registration.
28 Feb 2022
After all approved extensions.
—
Handover date, when available.
52 mo overdue51.8 mo
How far past deadline an ongoing project is.
1
More extensions can signal execution risk.
Complaints
Buyer complaints recorded on the official registry.
Complaints on this project
0
Complaints against the builder
0
No complaints found in the data we have. This isn't a guarantee — verify on the portal.
Extension history
Each time the completion deadline was officially pushed back.
| From | Extended to | Reason |
|---|---|---|
| 1 Sept 2021 | 28 Feb 2022 | 28-02-2022 (Six months extension in view of force majeure caused by covid-19 pandemic) |
About the builder
How this developer has performed across all their tracked projects.
Poor track record
Tracking 5 projects — 2 delivered, 3 still active. 5 of 5 (100%) ran late by an average of 6 months.
Official records
Builder: LOGIX INFRATECH PRIVATE LIMITED (NAME:LOGIX INFRATECH PRIVATE LIMITED)
Data last refreshed 20 Jun 2026.