CASA GRANDE-2
UPRERAPRJ4491
Behind schedule
This project is about 9 months past its latest deadline and is not yet marked completed.
Where this project stands
The journey from RERA registration to completion, in order.
Past deadline by ~8 months.
Registered with RERA
8 Aug 2017Original promised completion
31 Dec 2020The deadline the builder committed to at registration.
Revised deadline after extensions
6 Oct 2025Pushed back ~57 months across 2 extensions.
Today — still not completed
About 8 months past the latest deadline.
Timeline & delay
Key dates and how they compare to what was promised.
8 Aug 2017
When the project was registered with RERA.
31 Dec 2020
The deadline committed to at registration.
6 Oct 2025
After all approved extensions.
—
Handover date, when available.
9 mo overdue8.5 mo
How far past deadline an ongoing project is.
2
More extensions can signal execution risk.
Complaints
Buyer complaints recorded on the official registry.
Complaints on this project
0
Complaints against the builder
0
No complaints found in the data we have. This isn't a guarantee — verify on the portal.
Extension history
Each time the completion deadline was officially pushed back.
| From | Extended to | Reason |
|---|---|---|
| 31 Dec 2020 | 30 Jun 2021 | 30-06-2021 (Six months extension in view of force majeure caused by covid-19 pandemic) |
| 30 Jun 2021 | 6 Oct 2025 | — |
About the builder
How this developer has performed across all their tracked projects.
Good track record
Tracking 2 projects — 1 delivered, 1 still active. 1 of 2 (50%) ran late. Limited history — read the project list before drawing conclusions.
See EARTHCON CONSTRUCTIONS PRIVATE LIMITED's full track record →