BLOSSOM ZEST (PHASE 2 TOWER- D,E,F & CLUB)
UPRERAPRJ4834
Delivered — but late
This project was completed about 6 months after its original promised deadline.
Where this project stands
The journey from RERA registration to completion, in order.
Completed.
Registered with RERA
3 Aug 2017Original promised completion
31 Dec 2021The deadline the builder committed to at registration.
Revised deadline after extensions
30 Jun 2022Pushed back ~6 months across 1 extension.
Marked completed on the portal
Shown as completed on the official registry (no exact date scraped).
Timeline & delay
Key dates and how they compare to what was promised.
3 Aug 2017
When the project was registered with RERA.
31 Dec 2021
The deadline committed to at registration.
30 Jun 2022
After all approved extensions.
—
Handover date, when available.
6 mo delay6 mo
How late the finished project was.
1
More extensions can signal execution risk.
Complaints
Buyer complaints recorded on the official registry.
Complaints on this project
0
Complaints against the builder
0
No complaints found in the data we have. This isn't a guarantee — verify on the portal.
Extension history
Each time the completion deadline was officially pushed back.
| From | Extended to | Reason |
|---|---|---|
| 31 Dec 2021 | 30 Jun 2022 | 30-06-2022 (Six months extension in view of force majeure caused by covid-19 pandemic) |
About the builder
How this developer has performed across all their tracked projects.
Poor track record
Tracking 3 projects — 2 delivered, 1 still active. 3 of 3 (100%) ran late by an average of 6 months.
Official records
Builder: LOGIX CITY DEVELOPERS PVT.LTD. (NAME:LOGIX CITY DEVELOPERS PVT.LTD.)
Data last refreshed 21 Jun 2026.