OPULENCE PHASE A
UPRERAPRJ483588
Delivered — but late
This project was completed about 6 months after its original promised deadline.
Where this project stands
The journey from RERA registration to completion, in order.
Completed.
Registered with RERA
18 Mar 2019Original promised completion
30 Apr 2023The deadline the builder committed to at registration.
Revised deadline after extensions
29 Oct 2023Pushed back ~6 months across 1 extension.
Marked completed on the portal
Shown as completed on the official registry (no exact date scraped).
Timeline & delay
Key dates and how they compare to what was promised.
18 Mar 2019
When the project was registered with RERA.
30 Apr 2023
The deadline committed to at registration.
29 Oct 2023
After all approved extensions.
—
Handover date, when available.
6 mo delay6 mo
How late the finished project was.
1
More extensions can signal execution risk.
Complaints
Buyer complaints recorded on the official registry.
Complaints on this project
0
Complaints against the builder
0
No complaints found in the data we have. This isn't a guarantee — verify on the portal.
Extension history
Each time the completion deadline was officially pushed back.
| From | Extended to | Reason |
|---|---|---|
| 30 Apr 2023 | 29 Oct 2023 | 29-10-2023 (Six months extension in view of force majeure caused by covid-19 pandemic) |
About the builder
How this developer has performed across all their tracked projects.
Weak track record
Tracking 2 projects — 2 delivered, 0 still active. 1 of 2 (50%) ran late by an average of 3 months. Limited history — read the project list before drawing conclusions.
See SAHA ESTATE DEVELOPERS PRIVATE LIMITED's full track record →
Official records
Builder: SAHA ESTATE DEVELOPERS PRIVATE LIMITED (NAME:SAHA ESTATE DEVELOPERS PRIVATE LIMITED)
Data last refreshed 21 Jun 2026.