Jaypee Greens, E-9 Land 1, Greater Noida
UPRERAPRJ5014
Behind schedule
This project is about 64 months past its latest deadline and is not yet marked completed.
Where this project stands
The journey from RERA registration to completion, in order.
Past deadline by ~64 months.
Registered with RERA
29 Jul 2017Original promised completion
31 Aug 2020The deadline the builder committed to at registration.
Revised deadline after extensions
27 Feb 2021Pushed back ~6 months across 1 extension.
Today — still not completed
About 64 months past the latest deadline.
Timeline & delay
Key dates and how they compare to what was promised.
29 Jul 2017
When the project was registered with RERA.
31 Aug 2020
The deadline committed to at registration.
27 Feb 2021
After all approved extensions.
—
Handover date, when available.
64 mo overdue63.8 mo
How far past deadline an ongoing project is.
1
More extensions can signal execution risk.
Complaints
Buyer complaints recorded on the official registry.
Complaints on this project
0
Complaints against the builder
0
No complaints found in the data we have. This isn't a guarantee — verify on the portal.
Extension history
Each time the completion deadline was officially pushed back.
| From | Extended to | Reason |
|---|---|---|
| 31 Aug 2020 | 27 Feb 2021 | 27-02-2021 (Six months extension in view of force majeure caused by covid-19 pandemic) |
About the builder
How this developer has performed across all their tracked projects.
Poor track record
Tracking 35 projects — 21 delivered, 14 still active. 25 of 35 (71%) ran late by an average of 5 months.
Official records
Builder: JAIPRAKASH ASSOCIATES LIMITED (NAME:JAIPRAKASH ASSOCIATES LIMITED)
Data last refreshed 20 Jun 2026.