Imperial Heights (Phase 1)
RERA project status · delays · complaints
UPRERAPRJ504323
Under construction
Currently within its planned build window. Watch the deadline and any new extensions.
Where this project stands
The journey from RERA registration to completion, in order.
Approaching the deadline.
Registered with RERA
31 Aug 2019Original promised completion
1 Aug 2024The deadline the builder committed to at registration.
Revised deadline after extensions
30 Jan 2027Pushed back ~30 months across 3 extensions.
Today — in progress
About 6 months left until the deadline.
Timeline & delay
Key dates and how they compare to what was promised.
31 Aug 2019
When the project was registered with RERA.
1 Aug 2024
The deadline committed to at registration.
30 Jan 2027
After all approved extensions.
—
Handover date, when available.
On track0 mo
How far past deadline an ongoing project is.
3
More extensions can signal execution risk.
Complaints
Buyer complaints recorded on the official registry.
Complaints on this project
0
Complaints against the builder
0
No complaints found in the data we have. This isn't a guarantee — verify on the portal.
Extension history
Each time the completion deadline was officially pushed back.
| From | Extended to | Reason |
|---|---|---|
| 1 Aug 2024 | 31 Jan 2025 | 31-01-2025 (Six months extension in view of force majeure caused by covid-19 pandemic) |
| 31 Jan 2025 | 30 Jan 2026 | — |
| 30 Jan 2026 | 30 Jan 2027 | — |
Official records
Data last refreshed 20 Jun 2026.