Nirala Estate Phase-II
UPRERAPRJ519100
Delivered — but late
This project was completed about 6 months after its original promised deadline.
Where this project stands
The journey from RERA registration to completion, in order.
Completed.
Registered with RERA
28 Jan 2019Original promised completion
18 Nov 2024The deadline the builder committed to at registration.
Revised deadline after extensions
17 May 2025Pushed back ~6 months across 1 extension.
Marked completed on the portal
Shown as completed on the official registry (no exact date scraped).
Timeline & delay
Key dates and how they compare to what was promised.
28 Jan 2019
When the project was registered with RERA.
18 Nov 2024
The deadline committed to at registration.
17 May 2025
After all approved extensions.
—
Handover date, when available.
6 mo delay6 mo
How late the finished project was.
1
More extensions can signal execution risk.
Complaints
Buyer complaints recorded on the official registry.
Complaints on this project
0
Complaints against the builder
0
No complaints found in the data we have. This isn't a guarantee — verify on the portal.
Extension history
Each time the completion deadline was officially pushed back.
| From | Extended to | Reason |
|---|---|---|
| 18 Nov 2024 | 17 May 2025 | 17-05-2025 (Six months extension in view of force majeure caused by covid-19 pandemic) |
About the builder
How this developer has performed across all their tracked projects.
Weak track record
Tracking 4 projects — 4 delivered, 0 still active. 2 of 4 (50%) ran late by an average of 3 months.
Official records
Builder: NIRALA INFRATECH PRIVATE LIMITED (NAME:NIRALA INFRATECH PRIVATE LIMITED)