DEVIKA GOLD HOMZ

RERA project status · delays · complaints

UPRERAPRJ5398

Uttar PradeshCompleted

Delivered — but late

This project was completed about 12 months after its original promised deadline.

Where this project stands

The journey from RERA registration to completion, in order.

Registered 1 Aug 2017Due 29 Dec 2020

Completed.

  1. Registered with RERA

    1 Aug 2017
  2. Original promised completion

    31 Dec 2019

    The deadline the builder committed to at registration.

  3. Revised deadline after extensions

    29 Dec 2020

    Pushed back ~12 months across 2 extensions.

  4. Marked completed on the portal

    Shown as completed on the official registry (no exact date scraped).

Timeline & delay

Key dates and how they compare to what was promised.

1 Aug 2017

When the project was registered with RERA.

31 Dec 2019

The deadline committed to at registration.

29 Dec 2020

After all approved extensions.

—

Handover date, when available.

12 mo delay12 mo

How late the finished project was.

2

More extensions can signal execution risk.

On UP RERA this project's registration status is Completed. “Registration status” is the legal state of the filing; “completion status” is how far along construction is.

Complaints

Buyer complaints recorded on the official registry.

Complaints on this project

0

Complaints against the builder

0

No complaints found in the data we have. This isn't a guarantee — verify on the portal.

Extension history

Each time the completion deadline was officially pushed back.

FromExtended toReason
31 Dec 201930 Jun 2020—
30 Jun 202029 Dec 202029-12-2020 (Six months extension in view of force majeure caused by covid-19 pandemic)