Jaypee Greens Villa Sunnyvale Homes, Mirzapur
UPRERAPRJ5431
Delivered — but late
This project was completed about 6 months after its original promised deadline.
Where this project stands
The journey from RERA registration to completion, in order.
Completed.
Registered with RERA
29 Jul 2017Original promised completion
30 Jun 2021The deadline the builder committed to at registration.
Revised deadline after extensions
29 Dec 2021Pushed back ~6 months across 1 extension.
Marked completed on the portal
Shown as completed on the official registry (no exact date scraped).
Timeline & delay
Key dates and how they compare to what was promised.
29 Jul 2017
When the project was registered with RERA.
30 Jun 2021
The deadline committed to at registration.
29 Dec 2021
After all approved extensions.
—
Handover date, when available.
6 mo delay6 mo
How late the finished project was.
1
More extensions can signal execution risk.
Complaints
Buyer complaints recorded on the official registry.
Complaints on this project
0
Complaints against the builder
0
No complaints found in the data we have. This isn't a guarantee — verify on the portal.
Extension history
Each time the completion deadline was officially pushed back.
| From | Extended to | Reason |
|---|---|---|
| 30 Jun 2021 | 29 Dec 2021 | 29-12-2021 (Six months extension in view of force majeure caused by covid-19 pandemic) |
About the builder
How this developer has performed across all their tracked projects.
Poor track record
Tracking 25 projects — 18 delivered, 7 still active. 17 of 25 (68%) ran late by an average of 28 months.
Official records
Builder: JAYPEE INFRATECH LIMITED (NAME:JAYPEE INFRATECH LIMITED)
Data last refreshed 21 Jun 2026.