THE EXPRESS PARK VIEW II- LOW RISE APARTMENTS
UPRERAPRJ555694
Behind schedule
This project is about 17 months past its latest deadline and is not yet marked completed.
Where this project stands
The journey from RERA registration to completion, in order.
Past deadline by ~17 months.
Registered with RERA
31 Mar 2021Original promised completion
23 Jan 2024The deadline the builder committed to at registration.
Revised deadline after extensions
22 Jan 2025Pushed back ~12 months across 1 extension.
Today — still not completed
About 17 months past the latest deadline.
Timeline & delay
Key dates and how they compare to what was promised.
31 Mar 2021
When the project was registered with RERA.
23 Jan 2024
The deadline committed to at registration.
22 Jan 2025
After all approved extensions.
—
Handover date, when available.
17 mo overdue17 mo
How far past deadline an ongoing project is.
1
More extensions can signal execution risk.
Complaints
Buyer complaints recorded on the official registry.
Complaints on this project
0
Complaints against the builder
0
No complaints found in the data we have. This isn't a guarantee — verify on the portal.
Extension history
Each time the completion deadline was officially pushed back.
| From | Extended to | Reason |
|---|---|---|
| 23 Jan 2024 | 22 Jan 2025 | — |
About the builder
How this developer has performed across all their tracked projects.
Poor track record
Tracking 4 projects — 3 delivered, 1 still active. 3 of 4 (75%) ran late by an average of 8 months.
Official records
Builder: IITL-NIMBUS THE EXPRESS PARK VIEW (NAME:IITL-NIMBUS THE EXPRESS PARK VIEW)
Data last refreshed 20 Jun 2026.