Jaypee Greens, SV-14 Land 2, Greater Noida
UPRERAPRJ5605
Behind schedule
This project is about 88 months past its latest deadline and is not yet marked completed.
Where this project stands
The journey from RERA registration to completion, in order.
Past deadline by ~88 months.
Registered with RERA
30 Jul 2017Original promised completion
17 Feb 2019The deadline the builder committed to at registration.
Today — still not completed
About 88 months past the latest deadline.
Timeline & delay
Key dates and how they compare to what was promised.
30 Jul 2017
When the project was registered with RERA.
17 Feb 2019
The deadline committed to at registration.
17 Feb 2019
After all approved extensions.
—
Handover date, when available.
88 mo overdue88.1 mo
How far past deadline an ongoing project is.
0
More extensions can signal execution risk.
Complaints
Buyer complaints recorded on the official registry.
Complaints on this project
0
Complaints against the builder
0
No complaints found in the data we have. This isn't a guarantee — verify on the portal.
About the builder
How this developer has performed across all their tracked projects.
Poor track record
Tracking 7 projects — 0 delivered, 7 still active. 7 of 7 (100%) ran late.
Official records
Builder: JAIPRAKASH ASSOCIATES LIMITED (UPRERAPRM6273)
Data last refreshed 20 Jun 2026.