Jaypee Greens, E-6/7 Land 2, Greater Noida
UPRERAPRJ5743
Delivered on time
Marked completed on the registry on or before the promised deadline.
Where this project stands
The journey from RERA registration to completion, in order.
Completed.
Registered with RERA
30 Jul 2017Original promised completion
31 Aug 2019The deadline the builder committed to at registration.
Marked completed on the portal
Shown as completed on the official registry (no exact date scraped).
Timeline & delay
Key dates and how they compare to what was promised.
30 Jul 2017
When the project was registered with RERA.
31 Aug 2019
The deadline committed to at registration.
31 Aug 2019
After all approved extensions.
—
Handover date, when available.
On track0 mo
How far past deadline an ongoing project is.
0
More extensions can signal execution risk.
Complaints
Buyer complaints recorded on the official registry.
Complaints on this project
0
Complaints against the builder
0
No complaints found in the data we have. This isn't a guarantee — verify on the portal.
About the builder
How this developer has performed across all their tracked projects.
Poor track record
Tracking 35 projects — 21 delivered, 14 still active. 25 of 35 (71%) ran late by an average of 5 months.
Official records
Builder: JAIPRAKASH ASSOCIATES LIMITED (NAME:JAIPRAKASH ASSOCIATES LIMITED)