"1st - A Park View" - Gaur Yamuna City
RERA project status · delays · complaints
UPRERAPRJ574384
Delivered on time
Marked completed on the registry on or before the promised deadline.
Where this project stands
The journey from RERA registration to completion, in order.
Completed.
Registered with RERA
18 Nov 2020Original promised completion
13 Oct 2025The deadline the builder committed to at registration.
Marked completed on the portal
Shown as completed on the official registry (no exact date scraped).
Timeline & delay
Key dates and how they compare to what was promised.
18 Nov 2020
When the project was registered with RERA.
13 Oct 2025
The deadline committed to at registration.
13 Oct 2025
After all approved extensions.
—
Handover date, when available.
On track0 mo
How far past deadline an ongoing project is.
0
More extensions can signal execution risk.
Complaints
Buyer complaints recorded on the official registry.
Complaints on this project
0
Complaints against the builder
0
No complaints found in the data we have. This isn't a guarantee — verify on the portal.
Official records
Data last refreshed 21 Jun 2026.