SUPERTECH GOLF COUNTRY (PHASE-II)
UPRERAPRJ5854
Delivered — but late
This project was completed about 9 months after its original promised deadline.
Where this project stands
The journey from RERA registration to completion, in order.
Completed.
Registered with RERA
14 Aug 2017Original promised completion
30 Mar 2019The deadline the builder committed to at registration.
Revised deadline after extensions
31 Dec 2019Pushed back ~9 months across 1 extension.
Marked completed on the portal
Shown as completed on the official registry (no exact date scraped).
Timeline & delay
Key dates and how they compare to what was promised.
14 Aug 2017
When the project was registered with RERA.
30 Mar 2019
The deadline committed to at registration.
31 Dec 2019
After all approved extensions.
—
Handover date, when available.
9 mo delay9 mo
How late the finished project was.
1
More extensions can signal execution risk.
Complaints
Buyer complaints recorded on the official registry.
Complaints on this project
0
Complaints against the builder
0
No complaints found in the data we have. This isn't a guarantee — verify on the portal.
Extension history
Each time the completion deadline was officially pushed back.
| From | Extended to | Reason |
|---|---|---|
| 30 Mar 2019 | 31 Dec 2019 | — |
About the builder
How this developer has performed across all their tracked projects.
Weak track record
Tracking 4 projects — 4 delivered, 0 still active. 2 of 4 (50%) ran late by an average of 5 months.
See SUPERTECH TOWNSHIP PROJECT LIMITED's full track record →
Official records
Builder: SUPERTECH TOWNSHIP PROJECT LIMITED (NAME:SUPERTECH TOWNSHIP PROJECT LIMITED)
Data last refreshed 21 Jun 2026.