GRANDTHUM PHASE I
UPRERAPRJ585534
Delivered — but late
This project was completed about 39 months after its original promised deadline.
Where this project stands
The journey from RERA registration to completion, in order.
Completed.
Registered with RERA
2 Sept 2019Original promised completion
30 Jun 2023The deadline the builder committed to at registration.
Revised deadline after extensions
26 Sept 2026Pushed back ~39 months across 4 extensions.
Marked completed on the portal
Shown as completed on the official registry (no exact date scraped).
Timeline & delay
Key dates and how they compare to what was promised.
2 Sept 2019
When the project was registered with RERA.
30 Jun 2023
The deadline committed to at registration.
26 Sept 2026
After all approved extensions.
—
Handover date, when available.
39 mo delay38.9 mo
How late the finished project was.
4
More extensions can signal execution risk.
Complaints
Buyer complaints recorded on the official registry.
Complaints on this project
0
Complaints against the builder
0
No complaints found in the data we have. This isn't a guarantee — verify on the portal.
Extension history
Each time the completion deadline was officially pushed back.
| From | Extended to | Reason |
|---|---|---|
| 30 Jun 2023 | 29 Dec 2023 | 29-12-2023 (Six months extension in view of force majeure caused by covid-19 pandemic) |
| 29 Dec 2023 | 28 Dec 2024 | — |
| 28 Dec 2024 | 27 Sept 2025 | — |
| 27 Sept 2025 | 26 Sept 2026 | — |
About the builder
How this developer has performed across all their tracked projects.
Poor track record
Tracking 4 projects — 3 delivered, 1 still active. 3 of 4 (75%) ran late by an average of 39 months.
Official records
Builder: A L SOFTWEB PRIVATE LIMITED (NAME:A L SOFTWEB PRIVATE LIMITED)
Data last refreshed 21 Jun 2026.